NOTE: All questions are written and reviewed by licensed contractors who are actively working in the field.
The following questions are typical of the kind of items that are on the examination.
The correct answer is highlighted.
1. As part of the safety training process contractors' supervisors are required to conduct "tool box" or "tailgate" safety meetings. How often must these meetings be held?
- a. Daily
- b. At least once every ten working days
- c. At least once a month
- d. At least once a quarter
2. Which of the following items is a job-related direct cost?
- a. Trade Association membership dues
- b. Contractor's license renewal fee
- c. Performance bonds
- d. Office rent
3. What legal remedy can be pursued for nonpayment of funds owed to a contractor from a private job?
- a. Notify the city building official.
- b. File preliminary lien notice.
- c. Perfect the claim of the lien.
- d. File a Stop Notice.