- When engineering calculations are required for a sign, who is authorized to prepare these
calculations?
- a. a licensed mechanical engineer
- b. a licensed C45 (Electrical Sign) contractor
- c. a licensed civil engineer
- d. a licensed A (General Engineering) contractor
- When manufacturing a rain lip on an exterior exposed raceway, where on the raceway should
the rain lip be located?
- a. left side
- b. bottom
- c. right side
- d. top
- Whose guidelines/specifications should be followed when determining load capacities for
crane and lifting equipment?
- a. project manager and engineer
- b. building owner and architect
- c. project manager and the EPA
- d. equipment manufacturer and Cal/OSHA